최근 글

  • Five million ACC cells equal 2.7 to 3.6 months of nameplate outputOctober 15, 2026
  • A 160 MW battery’s six-week commissioning has two baselinesOctober 8, 2026
  • Two Cycles a Day Take 106.8 % of a Day, and the Retention Tier Shifts Cell Volume by 1.47 GWhOctober 1, 2026
  • Battwoo’s Second-Life EV Batteries — When an 80 % Acceptance Threshold Overlaps the Retirement Distribution, Incoming Screening Becomes the BottleneckSeptember 30, 2026
  • US storage set an energy record in Q2 as installed power fell 7%September 29, 2026
  • CATL Starts Trial Production in Debrecen — The Digits of the Defect-Rate Target, Not the Equipment, Set the Length of a Trial RunSeptember 29, 2026
  • A 0.45 pp read-rate gap means 10x exceptions
    Process,  Traceability

    Cell-ID Laser DPM Read Rate 99.5% vs 99.95%: How No-Reads Drive Exceptions per Shift and OEE

    July 3, 2026 /

    The read rate of a cell-ID direct part mark (DPM) is a probability defined at a single read point, but the line experiences it raised to the power of the number of read points each cell passes. Assuming 12 read points and 22,000 cells per shift, a 99.5% read rate generates 1,320 No-Read exceptions per shift, while 99.95% generates 132. Under the same assumptions, OEE falls from a baseline of 84.64% to 75.50% at 99.5% (−9.14 pp), but only to 84.13% at 99.95% (−0.51 pp). A DPM specification should therefore be defined not as "read rate X%" but by three items: verification grade immediately after marking (ISO/IEC 29158), allowable exceptions…

    read more
    ESS-neofab Comments Off on Cell-ID Laser DPM Read Rate 99.5% vs 99.95%: How No-Reads Drive Exceptions per Shift and OEE

    You May Also Like

    비전 시스템 도입 리드타임 막대 도식 — 모델 단계만 축소될 때 전체가 77.5 %로만 줄어드는 구조

    Even a tenfold faster model moves the whole by 1.29x — what “5 to 10 times faster commissioning” actually requires

    September 26, 2026
    그리드포밍 PCS FAT 택타임 비교 및 택타임 점유율 변화 도식

    Grid-Forming PCS Mandate Redesigns FAT Takt Time and the BMS-PCS-EMS Interface

    August 31, 2026
    엣지 AI 비전검사 인터페이스 3안 비교: 엣지 로컬 판정, 게이트웨이 집선, 클라우드 중앙집중의 응답시간과 Traceability 완전성 비교 도식

    Edge AI Vision Inspection and Battery-Pack Leak Testing: How Gateway Aggregation Affects Traceability Completeness

    August 27, 2026